Selective demolition of interior partitions, walls, flooring, and ceiling finishes is complete. Mechanical, electrical, and plumbing services have been cut and capped or removed in anticipation of new equipment to serve the remodeled space.
Installation of underground utilities on the lower level is in process and structural steel for the new stairwell connecting the main floor and lower level is complete. A significant amount of construction material has been stockpiled on site and framing for the new walls is underway.